RFI-2026-0480
Overdue
Critical
CH 248+700
Drainage chamber invert level mismatch at CH 248+700
Delhi-Mumbai Expressway Pkg-12Created by Sana Qureshi (Site Engineer)2026-04-22
SLA timer
2d 14hremaining
Due
2026-05-01
Aging
16 days
Workflow progress3/6 stages
Description
Site survey shows invert level at 218.45 m vs drawing DRG-DRN-0421 indicating 217.90 m. Request revised drawing or instruction.
Drawing References
DRG-DRN-0421
BOQ References
BOQ-5.1.7
Attachments (1)
site-survey.pdf
1.2 MB
Workflow
Drafted
Rohan Iyer · May 2
Submitted
Rohan Iyer · May 2
Under Review
Anjali Mehra · May 3
4
Response
Anjali Mehra · Pending
5
PMC Approval
Vikram Shah · —
6
Closure
Site Engineer · —
Details
DisciplineDrainage
ContractorTata Projects
Assigned toRajeev Kulkarni (PMC)
Created2026-04-22
Due date2026-05-01
Aging16 days
AI Insight
Similar RFIs in this discipline are typically resolved in 2.4 days. Predicted overdue risk: Medium.